document Mediated Delivery )

Project Timeline


Pre-Planning Phase (June 2002 to October 2002)

  • Develop specifications for, order, and install staff processing stations and document server
  • Begin modification of Prospero software to receive Ariel ® documents. Create a database-oriented user management system. Create customized data collection system
  • Work with libraries to assess current technical environment
  • Work with libraries to measure current document turnaround
  • Work with libraries to assess existing patron attitudes and expectations 
  • Work with libraries to create generic materials to support the marketing of the service at the project libraries.
  • Develop various statistical logs to track usage and problems.
  • Create a project Web site and email discussion list to communicate with library contacts

Phase One:  Planning (October 2002 to Jan 2003)

  • Complete modifications to Prospero software
  • Conduct orientations with all 6 Phase One libraries
  • Work with libraries to assess patron attitudes and expectations 
  • Work with libraries to begin marketing efforts
  • Run test documents to 2-3 Phase One sites

Phase One: Implementation (Jan 2003 to March 2003)

  • Roll out service to all 6 Phase One sites
  • Collect and analyze production data

Phase Two: Planning (March 2003 to June 2003)

  • Identify and make modifications to model based on the experiences of Phase One
  • Conduct orientations with all 11 Phase Two libraries
  • Work with libraries to assess patron attitudes and expectations 
  • Work with libraries to begin marketing efforts
  • Run test documents to 2-3 Phase Two sites

Phase Two: Implementation (June 2003- September 2003)

  • Roll out service to all 11 Phase Two sites
  • Collect and analyze production data

Operational Phase (September 2003 – December 2003)

  • Continue service to all 17 sites
  • Conduct orientations and roll out service to any new / additional sites
  • Modify processes as needed
  • Collect and analyze production data

Extension Phase (December 2003 – December 2004)

  • Develop email server for receving document attachments
  • Develop Odyssey system interoperability
  • Add additional project sites when requested
  • Modify processes as needed
  • Collect and analyze production data



docMD is funded through support by the National Network of Libraries of Medicine,
Greater Midwest Region. Ohio State University Project Number 743202

URL: http://docmd.med.ohio-state.edu/

Last updated by EHS on 9/24/2003